fbpx

Exam Assure Quiz for

RPSC

ATP Exam 2022

RPSC ATP Quiz-28

05 Questions- 05 Minutes

Identify the correct sequence of steps involved in project cost-benefit analysis.

Use codes to give correct answer.

  1. Specification of the project
  2. Evaluation of costs & benefits
  3. Listing cost elements & benefit elements
  4. Discounting the future to Its present value

Which is the discount rate which makes its net present value equal to zero?

"Development that meets the needs of the present, without compromising the ability of future generations, to meet their own needs." What is this development called?

Among the following, who are the main contributors to provide houses in urban area?

In rural housing development, one of the following agencies plays a major role in extending financial loans to the rural folk. What is that agency called?

Your score is

The average score is 61%

0%

Previous Quizzes:

For further queries, WhatsApp/Call:
+91 76317 66140

or Click the below button

error: Content is protected !!
× How can we help you?